Impermissible to calculate delay damages for additional labor costs based on comparison of pre-contract estimate of labor costs and actual labor costs.
A subcontractor on a city project brought an action for delay damages, and the defendant appealed an award in excess of $40 million following a non-jury trial, including $9.8 million in additional labor cost damages.