Presented by the Environmental and Toxic Tort Practice Group

Third Circuit Offers Further Clarity on Scope of Operator Liability Under § 107(a) of CERCLA

In a recent decision, the Third Circuit upheld the district court’s decision, finding that the government’s exercise of wartime controls of a chromium processing plant was insufficient to hold the government liable as an “operator” under Section 107(a) of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). PPG Indus. Inc. v. United States, No. 19-1165, slip op. (3d Cir. May 4, 2020). Beginning in around 1915, the site in question was operated by Natural Products Refining Corporation (NPRC) as a chemical plant, processing chromite ore into chromium chemicals, which were used for dyeing cloth and tanning leather. The process generated hazardous materials as waste byproducts, which were stockpiled outside and uncovered. As a result, the hazardous substances seeped into the surround soil and groundwater.

During World War I and World War II, the government designated chromium chemicals as “critical” war materials and implemented several controls, including price controls, labor controls and production controls. For price controls, the government controlled the price of the raw materials, the quantities of chromite ore that could be bought, to whom they could sell, how much they could sell and which of their purchase orders had priority. The orders, however, did not direct how the ores were to be processed, how the chromium was made or how it was handled.

As for labor controls, the government took various measures to prevent labor shortages, including efforts to improve working conditions, authorizing wage increases and calling in the Army to seize plants where workers were on strike. There was, however, no evidence that the NPRC site was ever seized by the government. As part of this effort, a suggestion was made by Army personnel that the NPRC site be operated seven days per week, rather than six. That change was subsequently implemented. Beginning in 1944, the NPRC site began operating on a seven-day work week.

With regard to production controls, the record showed three proposals that were considered to increase production. The first was to run the ore through the manufacturing process fewer times. This would decrease production times, but would increase waste since it left chromium in the waste sludge that would have otherwise been extracted in successive runs. Part of this option included a subsidy to help offset the cost of the more wasteful processing of the ore, but the subsidy was later rejected by another federal entity. Notwithstanding this, the record showed that NPRC did switch to the more wasteful process.

The second option was to use more expensive Russian ore. In order to offset the increased cost of the ore, another subsidy was proposed, but this subsidy was actually passed. The record, however, showed that NPRC rejected this option and never received any such subsidies.

The final option was to expand plant capacity. The chromium chemical manufactures generally opposed this option because they did not want new competition and, instead, tried to expand production. NPRC did initially secure government funding for an expansion, but later decided against it.

The plaintiff, PPG Industries, Inc., (PPG), bought the site from NPRC in 1954 and operated it essentially in the same manner as NPRC had done until 1963. Since 1990, PPG alleges it has spent $367 million remediating the site and surrounding areas. In 2012, PPG sued the government under Section 107(a) of CERCLA, alleging that its wartime controls over the site rendered it an “operator” of the site. PPG moved for summary judgment on the issue, and the government cross-moved. The District Court denied PPG’s motion and granted the government’s cross-motion. The District Court found that the government’s actions were consistent with general wartime influence over and industry and did not extend influence over the plant’s pollution-related activities. Thus, the District Court found that such activities were insufficient for operator liability under CERCLA.

In upholding the District Court’s decision, the Third Circuit clarified the proper standard to be applied in cases involving CERCLA liability under Section 107(a). The standard, according to the Third Circuit, (1) focuses on the relationship between the purported operator and the facility at issue, and (2) further focuses on operations specifically related to pollution. Thus, the Third Circuit held that operator liability only extends to those who “manage, direct, or control operations specifically related to pollution, that is, operations having to do with the leakage or disposal of hazardous waste or decisions about compliance with environmental regulations.” The court clarified that, under this standard, something more is required that “general control over an industry or facility – it requires some indicia of control over the facility’s polluting activities.”

Under this standard, the court held that general wartime control over an industry is insufficient. Specifically, in this case, the court found that the government did not control any operations related to pollution. The court noted that while the government did exert control over various aspects of the manufacturing process, such as the price of raw materials, the quantities of chromite ore that processors such as NPRC could buy, to whom they could sell, how much they could sell and which purchase orders had priority, it had no involvement and exerted no control over the pollution-causing activities. For example, the court noted that there was no evidence that the government was responsible for the practice of stockpiling the hazardous waste byproducts from the manufacturing process.

The court rejected PPG’s argument that there was a “nexus” between the government’s activities and “waste-disposal matters” at the site on the basis that the overall process, which the government was familiar with, was inherently hazardous-waste producing. The court held that mere knowledge of a hazardous waste-producing activity is not sufficient. For CERCLA operator liability to attach, the alleged operator must “manage, direct, or conduct operations specifically related to pollution.”

The court also rejected PPG’s argument regarding a nexus based on the government directing NPRC to switch to the quicker, more wasteful manufacturing process, since the record showed that the government did not force NPRC to make the switch but, instead, only “recommended” the change be made. Lastly, the court rejected PPG’s nexus argument on the basis of an alleged sludge subsidy provided by the government to NPRC, since the record showed that no such subsidy was actually and, therefore, no evidence that the government purchased the hazardous waste sludge.

Thus, the Third Circuit upheld the District Court’s decision finding that the government never specifically managed or conducted NPRC’s operations related to pollution. The District Court correctly found that the government’s actions in relation to NPRC’s plant were consistent with general wartime influence over an industry – not control over NPRC’s pollution-related actives.

In its holding, the court distinguished a similar case involving claims of operator liability against the government, FMC Corp. v. United States Department of Commerce, 29 F.3d 833 (3d Cir. 1994). In that case, the government: (1) built and retained ownership of new facilities near the plant; (2) had a representative on site; (3) ordered the facility to produce a different product; and (4) supplied employees to install equipment. Thus, the court noted that in FMC, “the government effectively seized total control of the plant’s operations by requiring the manufacturer to convert its plant to produce a different product and stepping in to help it achieve this goal, which included involvement in waste disposal.” This was different from the present case where NPRC was free to produce chromium before and after the wars, there was no government representative on site, the government was much less involved in labor decisions and not at all involved in waste disposal decisions. Lastly, rather than being directed by the government to employ a specific method for increasing output, NPRC itself chose the option that was most convenient for it.

This case clarifies the outer bounds of operator liability under Section 107(a) of CERCLA. Importantly, it clarifies that operator liability only extends to those who “manage, direct, or conduct operations specifically related to pollution, that is, operations having to do with leakage or disposal of hazardous waste or decisions about compliance with environmental regulations,” and that general control over an industry, or even a specific facility, will not be enough. In order to prevail on such claims, an indicia of control over the facility’s polluting activities is required. Therefore, general wartime control over an industry will be an insufficient basis upon which to hold the government liable.

 

The material in this law alert has been prepared for our readers by Marshall Dennehey Warner Coleman & Goggin. It is solely intended to provide information on recent legal developments, and is not intended to provide legal advice for a specific situation or to create an attorney-client relationship. We welcome the opportunity to provide such legal assistance as you require on this and other subjects. If you receive the alerts in error, please send a note tamontemuro@mdwcg.com. ATTORNEY ADVERTISING pursuant to New York RPC 7.1. © 2020 Marshall Dennehey Warner Coleman & Goggin. All Rights Reserved.